Wendover cycleway improvements

Cycleway improvements in Wendover began on 24 January 2022 and was mostly completed in May 2022.

To receive regular project updates during the construction phase, subscribe to our bulletin. This will be the main way we communicate during the project.

You can also view previous bulletins.

Current progress

Following a successful public consultation and completion of the detail designs for the scheme, construction began on 24 January 2022 and was mostly completed in May 2022. The project will improve the cycling and walking network and help promote sustainable travel in the town.

The work has included a combination of creating new stretches of cycleway, widening and resurfacing existing cycleways and footways and adding markings on roads and cycleway signage. All will combine to make it easier for cyclists and pedestrians to get around the town using a cohesive network.

Work has included linking the Amber Way cycleway, which currently goes from Aylesbury to Victory Road in Wendover, to Wendover railway station.

Additionally, there is a new widened cycleway between Halton Lane and Castle Park Road as well as improvements and widening along the existing cycleway between Halton Lane and Worlds End Lane.

A new extension to the Amber Way now connects the cycleway to the schools along Wharf Road.

Objectives

This project aims to:

  • improve connectivity in Wendover and therefore help promote sustainable travel
  • encourage cycling for shorter journeys in Wendover through developing the cycling network

Proposed cycleway improvements

With the available budget, these 3 cycleway improvements within Wendover are being completed.

The proposals are:

  • railway station access – linking the existing Amber Way cycleway along Aylesbury Road to the Railway Station
  • Amber Way improvements on Aylesbury Road between Halton Lane and Castle Park Road
  • school access – extending the existing Amber Way cycleway along Aylesbury Road towards the schools along Wharf Road

Funding

We have a budget of approximately £500,000 to spend on cycleway improvements, which is funded by HS2 Ltd.

Consultation

The Wendover Cycleway improvements consultation began on 1 March 2021 and ended on 28 March 2021.

The project team hosted the consultation through the project webpage and Your Voice Bucks. Roughly 1,000 leaflets were distributed to nearby properties to inform them about the consultation as well as social and mainstream media.

The project team have identified common queries, comments, and issues that were raised during the consultation process. These are grouped into themes and responses are set out within our Consultation Response Document PDF, 226KB.

Contact us

Sign up to receive project updates. This will be the main way we will communicate with everyone throughout the project.

If you have any queries contact us by email: [email protected]

Or you can send us your comments in writing at:

Wendover Cycleway Team
Highways Infrastructure Projects Team
Buckinghamshire Council
Floor 07
Walton Street Offices
Walton Street
Aylesbury
HP20 1UY