Complete a notification of commencement for building work

If you've received building regulations approval, you must tell us:

  • before building work starts
  • when building work has officially started

This helps us arrange inspections and make sure your project complies with building regulations requirements.

Notify us before work starts

You must tell us at least 2 working days before building work begins.

Notify us before building work starts

Notify us when work has started

You must tell us again within 5 working days of building work officially starting.

Notify us that building work has started

Definition of building work starting

For a new building, work is considered to have started when:

  • the foundations have been completed
  • the ground floor level has been built
  • any basement work has been completed, if applicable

For all other building work, work is considered to have started when at least 15% of the planned work has been completed.

What happens next

After submitting your notification, you must book a site inspection.