Complete a notification of commencement for building work
If you've received building regulations approval, you must tell us:
- before building work starts
- when building work has officially started
This helps us arrange inspections and make sure your project complies with building regulations requirements.
Notify us before work starts
You must tell us at least 2 working days before building work begins.
Notify us when work has started
You must tell us again within 5 working days of building work officially starting.
Definition of building work starting
For a new building, work is considered to have started when:
- the foundations have been completed
- the ground floor level has been built
- any basement work has been completed, if applicable
For all other building work, work is considered to have started when at least 15% of the planned work has been completed.
What happens next
After submitting your notification, you must book a site inspection.