Tell us you've started building works (complete a commencement form)
You need to tell us when you start working on a property.
When you need to tell us
You need to tell us twice:
- the first time, at least 2 working days before you intend to start work
- the second time, within 5 working days of the works 'commencing'
Work has 'commenced' when:
- for new build properties, you've built the ground floor level including all foundations and any basement or extensions
- for any other building work, 15% of the planned work has been completed
Tell us you're intending to commence work
Use our online form to tell us that work is commencing (at least 2 working days before you start).
Complete the form to tell us you're intending to commence work.
Tell us you have commenced work
Use our online form to tell us you have commenced the works (within 5 working days of the works commencing).
Complete the form to tell us that works have commenced.
Book a site inspection
After works have commenced, you'll need to book a site inspection.