Authority Monitoring Report 2023 to 2024
9. Housing
The AMR must report on policies that specify an annual number of net additional dwellings or additional affordable dwellings within the Council area. This includes completions, demolitions and outstanding commitments. For more housing information, see appendix 1 XLSX, 25KB.
Performance Against Current Targets
9.1. North & Central Areas
The annual local housing requirement target is 1,430 dwellings per annum. In the monitoring year, the delivery against this housing target was 961 (67%).
9.2. East Area
The annual local housing requirement target is 362 dwelling per annum. In the monitoring year, the delivery against this housing target was 147 (41%).
9.3. South Area
The annual local housing requirement target is 429 dwelling per annum. In the monitoring year, the delivery against this housing target was 263 (61%).
9.4. West Area
The housing requirement is 10,925 dwellings over the plan period 2013 to 2033.
The annualised requirement target is 546.25 dwellings per annum. In the monitoring year, the delivery against this housing target was 874 (160%).
Housing Delivery Test
The Housing Delivery Test (HDT) is an annual measurement of housing delivery and compares the net homes delivered over the previous 3 financial years to the homes required over the same period.
Buckinghamshire Council prepared a joint submission. The results for all authorities are available on the Housing Delivery Test webpage.
9.5. Homes Required
Council | Number of homes required 2020/21 | Number of homes required 2021/22 | Number of homes required 2022/23 | Total number of homes required |
---|---|---|---|---|
Buckinghamshire Council | 1649 | 2473 | 2477 | 6599 |
9.6. Homes Delivered
Council | Number of homes delivered 2020/21 | Number of homes delivered 2021/22 | Number of homes delivered 2022/23 | Total number of homes delivered |
---|---|---|---|---|
Buckinghamshire Council | 2031 | 2617 | 3718 | 8366 |
The 2023 HDT measurement achieved 127% and therefore no consequences are incurred.
9.7. Annual Housing Completions for all Areas since 2014
Year | North & Central | East | South | West |
---|---|---|---|---|
2014/15 | 1,355 | 114 | 139 | 423 |
2015/16 | 1,191 | 158 | 80 | 376 |
2016/17 | 1,309 | 221 | 411 | 788 |
2017/18 | 1,395 | 286 | 299 | 551 |
2018/19 | 1,758 | 353 | 328 | 814 |
2019/20 | 1,715 | 95 | 98 | 366 |
2020/21 | 1,357 | 146 | 121 | 357 |
2021/22 | 1,479 | 222 | 277 | 639 |
2022/23 | 1,980 | 287 | 479 | 1,005 |
2023/24 | 961 | 147 | 263 | 874 |
Total | 14,500 | 2,029 | 2,495 | 6,193 |
The figures for the East Area in 2019/20 and 2020/21 have been amended to 95 and 146 respectively to reflect previous discrepancies.
Completions and Demolitions
9.8. North & Central Areas
Area |
Net completions (brownfield) |
Net completions (greenfield) |
Total net completions |
Of which is office to residential permitted development (PD) |
Of which is storage to residential PD |
Of which is light industrial to residential PD |
Of which is other to residential PD |
---|---|---|---|---|---|---|---|
Aylesbury Area | 270 | 96 | 366 | 52 | 0 | 0 | 0 |
Buckingham | 32 | 14 | 46 | 1 | 0 | 0 | 0 |
Winslow | 1 | 47 | 48 | 0 | 0 | 0 | 0 |
Wendover | 1 | 1 | 2 | 0 | 0 | 0 | 0 |
Haddenham | 42 | 76 | 118 | 36 | 0 | 0 | 0 |
Rest of Rural Areas | 47 | 334 | 381 | 7 | 0 | 0 | 0 |
Total | 393 | 568 | 961 | 96 | 0 | 0 | 0 |
Major housing development for Buckinghamshire is defined as:
- Residential development of between 10 or more dwellings
- Residential development on a site area of 0.5 hectares or more where the number of dwellings is unknown
Area | Major Development Completions |
---|---|
Aylesbury Area | 403 |
Buckingham | 28 |
Winslow | 32 |
Wendover | 0 |
Haddenham | 105 |
Rest of Rural Areas | 263 |
Total | 831 |
Dwelling Type: House | Dwelling Type: Flat | Bedrooms per dwelling: 1 | Bedrooms per dwelling: 2 | Bedrooms per dwelling: 3 | Bedrooms per dwelling: 4 | Bedrooms per dwelling: 5+ |
---|---|---|---|---|---|---|
709 | 320 | 108 | 289 | 291 | 274 | 43 |
9.9. East Area
Area |
Net completions (brownfield) |
Net completions (greenfield) |
Total net completions |
Of which is office to residential permitted development (PD) |
Of which is storage to residential PD |
Of which is light industrial to residential PD |
Of which is other to residential PD |
---|---|---|---|---|---|---|---|
Amersham | 8 | 0 | 8 | 1 | 0 | 0 | 0 |
Ashley Green | 6 | 0 | 6 | 0 | 0 | 0 | 0 |
Chalfont St Giles | 7 | 0 | 7 | 0 | 0 | 0 | 0 |
Chalfont St Peter | 21 | 3 | 24 | 0 | 0 | 0 | 2 |
Chartridge | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Chenies | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Chesham Bois | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Chesham | 71 | 0 | 71 | 13 | 0 | 0 | 0 |
Cholesbury-cum-St. Leonards | 1 | 0 | 1 | 0 | 0 | 0 | 0 |
Coleshill | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Great Missenden | 12 | 0 | 12 | 0 | 0 | 0 | 0 |
Latimer & Ley Hill | 5 | 0 | 5 | 0 | 0 | 0 | 1 |
Little Chalfont | 7 | 0 | 7 | 4 | 0 | 0 | 0 |
Little Missenden | 2 | 0 | 2 | 0 | 0 | 0 | 1 |
Penn | 1 | 0 | 1 | 0 | 0 | 0 | 0 |
Seer Green | 2 | 0 | 2 | 0 | 0 | 0 | 0 |
The Lee | 1 | 0 | 1 | 0 | 0 | 0 | 0 |
Total | 144 | 3 | 147 | 18 | 0 | 0 | 4 |
Area |
Major Development Completions |
---|---|
Amersham | 10 |
Chesham | 47 |
Total | 57 |
Dwelling Type: House | Dwelling Type: Flat | Bedrooms per dwelling: 1 | Bedrooms per dwelling: 2 | Bedrooms per dwelling: 3 | Bedrooms per dwelling: 4 | Bedrooms per dwelling: 5+ |
---|---|---|---|---|---|---|
122 | 86 | 66 | 48 | 36 | 29 | 28 |
9.10. South Area
Area |
Net completions (brownfield) |
Net completions (greenfield) |
Total net completions |
Of which is office to residential permitted development (PD) |
Of which is storage to residential PD |
Of which is light industrial to residential PD |
Of which is other to residential PD |
---|---|---|---|---|---|---|---|
Beaconsfield | 25 | 0 | 25 | 0 | 0 | 0 | 0 |
Burnham | 135 | 2 | 137 | 10 | 0 | 0 | 0 |
Denham | -4 | 0 | -4 | 0 | 0 | 0 | 0 |
Dorney | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Farnham Royal | 50 | 2 | 52 | 0 | 0 | 0 | 0 |
Fulmer | 1 | 0 | 1 | 0 | 0 | 0 | 0 |
Gerrards Cross | 31 | 0 | 31 | 12 | 0 | 0 | 4 |
Hedgerley | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Iver | 8 | 0 | 8 | 0 | 0 | 0 | 3 |
Stoke Poges | 10 | 0 | 10 | 0 | 0 | 0 | 0 |
Taplow | 4 | 1 | 5 | 0 | 0 | 0 | 0 |
Wexham | -2 | 0 | -2 | 0 | 0 | 0 | 0 |
Total | 258 | 5 | 263 | 22 | 0 | 0 | 7 |
Area |
Major Development Completions |
---|---|
Burnham | 126 |
Farnham Royal | 23 |
Gerrards Cross |
12 |
Total | 161 |
Dwelling Type: House | Dwelling Type: Flat | Bedrooms per dwelling: 1 | Bedrooms per dwelling: 2 | Bedrooms per dwelling: 3 | Bedrooms per dwelling: 4 | Bedrooms per dwelling: 5+ |
---|---|---|---|---|---|---|
107 | 213 | 93 | 112 | 54 | 20 | 41 |
9.11. West Area
Tier |
Net completions (brownfield) |
Net completions (greenfield) |
Total net completions |
Of which is office to residential permitted development (PD) |
Of which is storage to residential PD |
Of which is light industrial to residential PD |
Of which is other to residential PD |
---|---|---|---|---|---|---|---|
Tier 1: High Wycombe | 422 | 65 | 487 | 67 | 0 | 0 | 0 |
Tier 2: Marlow, Princes Risborough, Bourne End/Wooburn |
120 | 0 | 120 | 39 | 0 | 0 | 0 |
Tier 3: Flackwell Heath & Lane End |
145 | 17 | 162 | 0 | 0 | 0 | 0 |
Tier 4: Longwick | 44 | 28 | 72 | 0 | 0 | 0 | 0 |
Tiers 5, 6 & Rural Areas |
10 | 23 | 33 | 0 | 0 | 0 | 0 |
Total | 741 | 133 | 874 | 106 | 0 | 0 | 0 |
Tier |
Major Development Completions |
---|---|
Tier 1: High Wycombe | 389 |
Tier 2: Marlow, Princes Risborough, Bourne End/Wooburn | 90 |
Tier 3: Flackwell Heath & Lane End | 153 |
Tier 4: Longwick | 62 |
Tiers 5, 6 & Rural Areas | 18 |
Total | 712 |
Dwelling Type: House | Dwelling Type: Flat | Bedrooms per dwelling: 1 | Bedrooms per dwelling: 2 | Bedrooms per dwelling: 3 | Bedrooms per dwelling: 4 | Bedrooms per dwelling: 5+ |
---|---|---|---|---|---|---|
222 | 684 | 370 | 354 | 96 | 63 | 47 |
Outstanding Commitments
9.12. North & Central Areas
Area |
Outstanding Commitments Not Yet Started |
Outstanding Commitments Under Construction |
---|---|---|
Aylesbury Area | 585 | 1,024 |
Buckingham | 571 | 17 |
Winslow | 170 | 287 |
Wendover | 3 | 0 |
Haddenham | 148 | 176 |
Rest of Rural Areas | 6,407 | 251 |
Total | 7,884 | 1,755 |
9.13. East Area
Area |
Outstanding Commitments Not Yet Started |
Outstanding Commitments Under Construction |
---|---|---|
Amersham | 13 | 8 |
Ashley Green | 5 | 0 |
Chalfont St Giles | 33 | 6 |
Chalfont St Peter | 23 | 346 |
Chartridge | 2 | 1 |
Chenies | 0 | 2 |
Chesham Bois | 3 | 1 |
Chesham | 11 | 42 |
Cholesbury-cum-St. Leonards | 0 | 1 |
Coleshill | 2 | 4 |
Great Missenden |
12 | 7 |
Latimer & Ley Hill | 2 | 0 |
Little Chalfont |
398 | 3 |
Little Missenden |
11 | 4 |
Penn | 12 | 5 |
Seer Green |
35 | 0 |
The Lee | 0 | 1 |
Total | 562 | 431 |
9.14. South Area
Area |
Outstanding Commitments Not Yet Started |
Outstanding Commitments Under Construction |
---|---|---|
Beaconsfield | 278 | 21 |
Burnham | 45 | 9 |
Denham | 166 | 13 |
Dorney | 3 | 0 |
Farnham Royal | 24 | 9 |
Fulmer | 4 | 2 |
Gerrards Cross | 41 | 82 |
Hedgerley | 1 | 2 |
Iver | 75 | 13 |
Stoke Poges | 11 | 4 |
Taplow | 26 | 10 |
Wexham | 6 | 7 |
Total | 680 | 172 |
9.15. West Area
Tier | Outstanding Commitments Not Yet Started | Outstanding Commitments Under Construction |
---|---|---|
Tier 1: High Wycombe | 817 | 271 |
Tier 2: Marlow, Princes Risborough, Bourne End/Wooburn |
323 | 49 |
Tier 3: Flackwell Heath & Lane End |
20 | 1 |
Tier 4: Longwick |
70 | 54 |
Tiers 5, 6 & Rural Areas |
67 | 32 |
Total | 1,297 | 407 |
Affordable Housing
9.16. North & Central Areas
Area | Affordable Housing Completions | Affordable Housing Not Yet Started | Affordable Housing Under Construction |
---|---|---|---|
Aylesbury Area | 111 | 24 | 152 |
Buckingham | 8 | 86 | 0 |
Winslow | 12 | 1 | 100 |
Wendover | 0 | 1 | 0 |
Haddenham | 15 | 0 | 0 |
Rest of Rural Areas | 49 | 2 | 26 |
Total | 195 | 114 | 278 |
Affordable housing completions are recorded differently between Planning Policy and Housing. This AMR uses the completions based on monitoring undertaken by Planning Policy.
9.17. East Area
Area | Affordable Housing Completions | Affordable Housing Not Yet Started | Affordable Housing Under Construction |
---|---|---|---|
Amersham | 0 | 0 | 1 |
Chalfont St Giles |
0 | 15 | 0 |
Chalfont St Peter |
0 | 4 | 43 |
Chesham | 34 | 0 | 0 |
Seer Green |
0 | 12 | 0 |
Total | 34 | 31 | 44 |
9.18. South Area
Area | Affordable Housing Completions | Affordable Housing Not Yet Started | Affordable Housing Under Construction |
---|---|---|---|
Beaconsfield | 0 | 0 | 0 |
Burnham | 70 | 8 | 0 |
Gerrards Cross |
0 | 0 | 1 |
Iver | 0 | 9 | 0 |
Total | 70 | 17 | 1 |
9.19. West Area
Tier | Affordable Housing Completions | Affordable Housing Not Yet Started | Affordable Housing Under Construction |
---|---|---|---|
Tier 1: High Wycombe |
70 | 112 | 133 |
Tier 2: Marlow, Princes Risborough, Bourne End/Wooburn |
0 | 78 | 0 |
Tier 3: Flackwell Heath & Lane End |
6 | 0 | 0 |
Tier 4: Longwick | 28 | 23 | 25 |
Tiers 5, 6 & Rural Areas |
9 | 0 | 10 |
Total | 113 | 213 | 168 |
Specialist Accommodation
Specialist accommodation refers to Class C2 residential institutions which includes residential care homes, hospitals, nursing homes, boarding schools, residential colleges and training centres.
9.20. North & Central Areas
There were 110 net specialist C2 accommodation bedrooms delivered during this monitoring period.
There are 0 net specialist C2 bedrooms proposed within outstanding commitments.
9.21. East Area
There were 58 net specialist C2 accommodation bedrooms delivered during this monitoring period.
There are -26 net specialist C2 bedrooms proposed within outstanding commitments.
9.22. South Area
There were 12 net specialist C2 accommodation bedrooms delivered during this monitoring period.
There are 84 net specialist C2 bedrooms proposed within outstanding commitments.
9.23. West Area
There were -63 specialist C2 accommodation bedrooms delivered during this monitoring period.
There are 7 specialist C2 bedrooms proposed within outstanding commitments.
Gypsies, Travellers and Travelling Showpeople
The Council needs to recognise and consider the needs of Gypsies, Travellers and Travelling Showpeople groups.
Area | Number of Permitted Pitches |
---|---|
North & Central | 10 |
West | 0 |
East | 0 |
South | 0 |
Total | 10 |