New road: Princes Risborough Southern Road Links (PRSRL)

The construction of a new railway underpass and link road as part of the wider Princes Risborough expansion area.

Construction work start date: spring 2024

Project completion date: autumn 2025

Location of works

Summerleys Road (B4444) to Picts Lane

Map showing the location plan of the PRSRL scheme

Location plan of PRSRL scheme

Projects aims

The Wycombe Local Plan (adopted 2009) allocates around 2,500 new homes in Princes Risborough through a major expansion to the north west of the town.

The PRSRL scheme is the first phase of the Princes Risborough relief road, which we'll build in 3 phases to support the expansion of the town.

The road will:

  • provide a complete alternative route to the existing A4010
  • connect the expansion area with the town
  • support the delivery of new homes
  • ease congestion on existing roads

Anticipated key project dates

Date Works

Spring to summer 2022

Submission of a full planning application

Spring 2022 to summer 2023

Start of land negotiations and acquisition

Late 2022 to early 2023

Statutory planning consultation and planning application determination

Summer 2023

Completion of scheme design and discharge of planning conditions

Spring 2024

Completion of land acquisition and agreements

Start of construction work

Autumn 2025

End of construction work

Keep up to date

For progress and traffic updates sign up to receive emails.

Sign up for project updates

Learn more about the project

Find out more about the project's progress, next steps, funding and consultation outcome.

Contact us

For more information about this project contact us by email: [email protected].