Weekly roadworks update 23/11/2020

During the course of next week Transport for Buckinghamshire will be carrying out work at the following locations as part of the Strategic Highway Maintenance Programme.

The works are part of a rolling programme of county-wide work. As some activities are weather dependent, dates may change at short notice.

Weekend working will only take place where specifically mentioned.

Carriageway schemes

Conventional surfacing programme

  • Townsend Road, Chesham - Broad Street to Bellingdon Road (Monday 23 November) - carriageway surfacing works using a road closure in operation between 7:30am and 6:00pm
  • Station Road, Beaconsfield – London End to 2nd entrance on Grove Road (Wednesday 25 November to Wednesday 16 December) - carriageway surfacing works using a road closure in operation between 7:30am and 6:00pm

Micro surfacing programme

  • Queens Road/ Harlow Road, High Wycombe – various locations along length of road (Monday 23 November to Wednesday 25 November) - carriageway Iron Works using localised traffic management and temporary traffic signals with a road closure in operation on Queens Road on Tuesday 24 between 7:00am and 7:00pm
  • Kelvin Close, High Wycombe - various locations along length of road (Wednesday 25 November) - carriageway Iron Works using localised traffic management and temporary traffic signals in operation between 7:00am and 7:00pm
  • Woodlands, Gerrards Cross - various locations along length of road (Thursday 26 to Friday 27 November) - carriageway Iron Works using localised traffic management in operation between 8:00am and 4:00pm
  • Lovel Road, Chalfont St Peter - various locations along length of road (Saturday 28 November) weekend working - carriageway Iron Works using localised traffic management in operation between 7:00am and 7:00pm

Bridge improvement programme

  • Station Road, Loudwater - A40 Junction with Station Road to Bucks Free Press building (Monday 23 November to Friday 4 December) - retaining Wall Refurbishment using temporary traffic signals in operation 24/7

Footway structural repair programme

  • Cottesloe Road, Aylesbury – Churchill Avenue to Clover Lane (Monday 23 November to Friday 27 November) - footway Improvement works using localised traffic management in operation between 7:30am and 4:30pm
  • London Road, Great Missenden - School Playing Field Entrance to Fire Station (Monday 23 November) - footway Improvement works using temporary traffic signals in operation between 9:30am and 3:30pm (3:00pm during school term time)
  • Coombe Gardens, Hughenden – Coombe Hill to Wedgewood Drive (Monday 23 November to Friday 4 December) - footway Improvement works using localised traffic management in operation between 7:30am and 4:30pm
  • Wedgewood Drive, Hughenden – Coombe Hill to Trees Avenue ( Monday 23 November to Friday 4 December) - footway Improvement works using localised traffic management in operation between 7:30am and 4:30pm

Drainage improvement schemes

  • Missenden Road/Wey Lane/Church Street, Chesham (Monday 23 November to Wednesday 23 December) - installation of new culvert using a road closure in operation 24/7
  • A4020 Oxford Road, Denham (Monday 23 November) - jetting Investigation Works using lane closures in operation between 9.30am and 3.30pm
  • Iver lane, Iver (Monday 23 November to Tuesday 24 November) - jetting, CCTV and drainage ditch clearance works using 2 way traffic lights in operation between 9.30am to 3.30pm